TSMC Acknowledges Power Cut at Arizona Fab, Rumors of Scrapped Wafers Emerge

Earlier this week, Tim Culpan (of Culpium newsletter fame), claimed that TSMC Arizona's flagship Fab 21 production facility experienced a major power cut around mid-September. The Taipei-based journalist has gathered information about this unfortunate incident from unnamed semiconductor industry figures. An unwanted interruption—supposedly caused by an outsourced industrial gas vendor—affected: "the flow of crucial inputs needed for chip making, forcing the facility to shut down for at least a few hours...As a result, the company had to scrap thousands of wafers that were in production for clients at the site which include Apple, NVIDIA, and AMD." Earlier today, a TSMC representative confirmed—to Tom's Hardware—that a power outage did occur, but did not disclose any details regarding the loss of wafers.

The Culpium insider article loosely connects the aforementioned incident to an apparent drop in TSMC Arizona profits—around the third quarter of this year. Culpan outlined some minor fallout effects: "impact to clients is likely to be negligible, I was told, and the financial loss to TSMC may be covered by insurance. Capacity at Fab 21 is still quite small, and many products being made there have already been taped out and manufactured in Taiwan previously. In past disruptions, lost production and revenue was made up in the subsequent quarter." Roughly ten months ago, the semiconductor giant's home operations were affected by an earthquake. Industry moles reckoned that (up to) 20,000 wafers were damaged during this wave of seismic activity; deemed to be very minor setback. The various fabs apparently bounced back swiftly into 24/7 production mode.
Sources: Tim Culpian (Culpium), Tom's Hardware, Data Centre Dynamics, CNBC (image source)
Add your own comment

23 Comments on TSMC Acknowledges Power Cut at Arizona Fab, Rumors of Scrapped Wafers Emerge

#2
Vya Domus
Seems like the entire tech sector is becoming entangled in a complex web of lies.
Posted on Reply
#3
kondamin
Production needing to stop because some gas flow at a third party faltered is one serious issue, don't they have reserves to last a decent amount of time?
Posted on Reply
#4
AVATARAT
Rise of price is coming.
Posted on Reply
#5
Space Lynx
Astronaut
LOL I PREDICTED THIS WHEN THEY STARTED BUILDING IN ARIZONA lmao, god it hurts sometimes being smarter than those MBA six figure bitches
Posted on Reply
#6
A&P211
Space LynxLOL I PREDICTED THIS WHEN THEY STARTED BUILDING IN ARIZONA lmao, god it hurts sometimes being smarter than those MBA six figure bitches
Why dont you work for them?
Posted on Reply
#7
Space Lynx
Astronaut
A&P211Why dont you work for them?
because my guess is you need an MBA
Posted on Reply
#8
TheinsanegamerN
Space Lynxbecause my guess is you need an MBA
So...why dont you have yours? If you have these incredible observational powers to be able to predict industrial gas shortages in Arizona, then you should be able to make REAL easy money in the industry.
Posted on Reply
#9
Space Lynx
Astronaut
TheinsanegamerNSo...why dont you have yours? If you have these incredible observational powers to be able to predict industrial gas shortages in Arizona, then you should be able to make REAL easy money in the industry.
i called a shortage a few years ago on this, i guess it was the wrong i pointed out though, oh well, also talked about water shortages in depth being in the future in that region in other threads, probably will still come true in about 5-10 years and the plants will be forced to shut down temporarily, but who knows
Space Lynx in TSMC's Morris Chang Says Arizona Fab Will Produce 3 nm Chips in the Futurehttps://arstechnica.com/science/2023/06/no-groundwater-no-new-homes-as-arizona-severely-restricts-new-housing/ lmao.
Posted on Reply
#10
Visible Noise
TheinsanegamerNSo...why dont you have yours? If you have these incredible observational powers to be able to predict industrial gas shortages in Arizona, then you should be able to make REAL easy money in the industry.
They should be able to test out and just get the degree with how smart they are. I’m sure TSMC will pour down their gratitude for them having saved the company.

Either that, or I had them on ignore and made the mistake of looking at what you replied to.
Six of my brain cells committed suicide thanks to you. :D
Posted on Reply
#11
TumbleGeorge
Why are the conditions for (in this case high-tech) manufacturing in the US so unstable?
Posted on Reply
#12
Jtuck9
In particular, it will be interesting to see both whether all these LLMs have a genuine, positive impact on science (or just produce a lot of queries that go nowhere, a digital version of the infamous never-built Gravina Island Bridge) and whether this is the last government subsidy of the AI industry, or just the first of many.

Has the bailout of generative AI already begun?

Or is pouring a pile of government money in just a coincidence?

garymarcus.substack.com/p/has-the-bailout-of-generative-ai

www7.bbk.ac.uk/hiddenpersuaders/blog/the-market-enchanters-mind-control-in-the-history-of-advertising/
Posted on Reply
#13
A&P211
TheinsanegamerNSo...why dont you have yours? If you have these incredible observational powers to be able to predict industrial gas shortages in Arizona, then you should be able to make REAL easy money in the industry.
I would ask him/her to work on wall street, he/she can predict the price of gold.

Dear sir/mam, where thy the price of gold go!!!¿¿??
Posted on Reply
#14
Jtuck9
A&P211I would ask him/her to work on wall street, he/she can predict the price of gold.

Dear sir/mam, where thy the price of gold go!!!¿¿??
I got recommended the Youtube Channel "Sidetrack Adventures" the other day. Fascinating insight with the backdrop of a desert...
Posted on Reply
#15
Scrizz
TumbleGeorgeWhy are the conditions for (in this case high-tech) manufacturing in the US so unstable?
It's not the entire US. It's where they decided to build it. They literally built it in the desert, the Sonoran Desert.
Posted on Reply
#16
TumbleGeorge
ScrizzIt's not the entire US. It's where they decided to build it. They literally built it in the desert, the Sonoran Desert.
If was builded coastal in Florida, I suppose that employees will be found more on the beach than in their work places in the fab.
Posted on Reply
#17
Scrizz
TumbleGeorgeIf was builded coastal in Florida, I suppose that employees will be found more on the beach than in their work places in the fab.
There's a lot more to the US than just Arizona and Florida. 🤷‍♂️
Intel picked Ohio for their latest fabs(It's not a desert or a beach :laugh:), but I'm guessing TSMC wanted to poach some of the Intel fab people from Chandler. ;)
Posted on Reply
#18
remixedcat
Space LynxLOL I PREDICTED THIS WHEN THEY STARTED BUILDING IN ARIZONA lmao, god it hurts sometimes being smarter than those MBA six figure bitches
And that state is a desert with huge heat. which means higher demands for everything! Ohio makes more sense. Moderate climate and natural gas is easier to come by.
Posted on Reply
#19
Space Lynx
Astronaut
remixedcatAnd that state is a desert with huge heat. which means higher demands for everything! Ohio makes more sense. Moderate climate and natural gas is easier to come by.
ya, I mentioned this is an article on tpu about 4 or 5 years ago, how water shortages etc would make this entire situation a mess.

can't find the link right now, but I did look. I know I posted it and talked about it with @TheLostSwede but i don't know where the actual article link is where i said that anymore. oh well
Posted on Reply
#20
remixedcat
Space Lynxya, I mentioned this is an article on tpu about 4 or 5 years ago, how water shortages etc would make this entire situation a mess.

can't find the link right now, but I did look. I know I posted it and talked about it with @TheLostSwede but i don't know where the actual article link is where i said that anymore. oh well
was it the intel fab one?
Posted on Reply
#22
Scrizz
TheinsanegamerNSo...why dont you have yours? If you have these incredible observational powers to be able to predict industrial gas shortages in Arizona, then you should be able to make REAL easy money in the industry.
I mean.... if you can't see a problem with building a natural resource hog, such as a fab, in a desert, I don't know what to tell you.
Posted on Reply
#23
TumbleGeorge
ScrizzI mean.... if you can't see a problem with building a natural resource hog, such as a fab, in a desert, I don't know what to tell you.
Yes problem solved 😁
... when complete cycle from sand to chip on place.