Intel's Fab 52 is Bigger Than TSMC Arizona, Produces More Than 40,000 Wafers Per Month

Intel Foundry has massive capacity in the United States, with its size surpassing that of TSMC's Arizona campus in terms of production capacity and building space. A CNBC crew visited Intel's Fab 52 in Arizona to explore its operations, uncovering some intriguing details about wafer capacity and future production plans. According to their report, Intel's Fab 52 produces approximately 10,000 wafers per week, totaling over 40,000 wafers per month. These wafers are manufactured using the 18A node, Intel's most advanced design, featuring innovations such as a backside power delivery network and gate-all-around transistors, among others.

Compared to TSMC's facility in Arizona, Intel's manufacturing capacity and node designs are superior. TSMC currently produces about 20,000 wafers per month at the older N5 and N4 nodes, which are 5 nm class, in the Fab 21 Phase 1 stage. Although TSMC plans to expand Fab 21 to increase wafer capacity and introduce more advanced nodes, these advancements will primarily remain in Taiwan, keeping U.S.-based TSMC production a few generations behind. Intel, on the other hand, has a limited number of external partners using its nodes, with the 18A node being primarily for Intel's own products, including the upcoming "Panther Lake" processor, and some future generations.
However, despite producing more wafers than TSMC, Intel's current yields are lower than TSMCs, giving Intel less usable silicon for these wafers. The "Panther Lake" design is early in its yield curve improvement, with yields on the Intel 18A node increasing by approximately 7% each month. The Fab 52 facility already includes at least one of ASML's most advanced Low-NA EUV systems, the NXE:3800E. This system features upgraded components such as enhanced wafer handlers, faster stages, and improved light sources derived from next-generation High-NA tools, enabling a production rate of 220 wafers per hour. Complementing this flagship system are three NXE:3600D scanners, each capable of processing 160 wafers per hour. Overall, Intel's Arizona operations are expected to house at least 15 EUV scanners in total.
Sources: CNBC, via Tom's Hardware
Add your own comment

20 Comments on Intel's Fab 52 is Bigger Than TSMC Arizona, Produces More Than 40,000 Wafers Per Month

#1
londiste
Interesting tidbit is that Intel's Fab 52 and TSMC Arizona are very close together. 50 miles or 80 km from each other :)
Posted on Reply
#2
docnorth
That's promising, but for now Intel's foundry should be mostly compared with TSMC's main facilities in Taiwan.
Posted on Reply
#3
kondamin
More tsmc in the article than intel about which it supposedly is...
Posted on Reply
#5
mb194dc
Bigger foundries to product more chips to be put in to data centres where they have no profitable use cases?
Posted on Reply
#6
Tomorrow
An American company with multiple fabs and decades of operation on US soil surpassing TSMC that has only built a single fab in US a few years ago?
Shocking. Truly shocking. Who could have foreseen this?

If Intel produces 40k wafers a month on 18A then why didn't Panther Lake launch in Q4 2025 like they promised? Unless they plan on releasing it in the next 7 days they've lied, again.

It doesn't matter how advanced their node is on paper. Success will be judged on how many can they ship (yields) and what are the product characteristics when tested by independent reviewers in terms of power, performance and area of performance (chip size relative to it's performance).
Posted on Reply
#7
Guwapo77
Way off topic here... But why in the heck did they both decide to build fabs in the freaking desert? I mean...water is needed and all they have to use is ground water. I would have bult it right off the Mississippi River or around the Great Lakes. That goes for Intel and TSMC...Arizona couldn't give me enough tax deductions to build there.
Posted on Reply
#8
Wirko
londisteInteresting tidbit is that Intel's Fab 52 and TSMC Arizona are very close together. 50 miles or 80 km from each other :)
This makes it easier to create a single point of failure. Shared power lines? Water shortage? Tumbleweeds?
Posted on Reply
#9
Tomorrow
WirkoThis makes it easier to create a single point of failure. Shared power lines? Water shortage? Tumbleweeds?
Tumbleweeds :laugh:
Guwapo77Way off topic here... But why in the heck did they both decide to build fabs in the freaking desert? I mean...water is needed and all they have to use is ground water. I would have bult it right off the Mississippi River or around the Great Lakes. That goes for Intel and TSMC...Arizona couldn't give me enough tax deductions to build there.
I think it has been certainly been discussed. Possibly qualified workforce related. Besides most of the water is very efficiently recycled in most fabs, so aside from some inevitable losses and the initial volume it's should not be a problem. Im more baffled by the the heat aspect. Cooling is not easy and it's even harder in Arizona. Then again this isn't a server farm so i presume the cooling requirements are lower.
Posted on Reply
#10
Guwapo77
TomorrowTumbleweeds :laugh:

I think it has been certainly been discussed. Possibly qualified workforce related. Besides most of the water is very efficiently recycled in most fabs, so aside from some inevitable losses and the initial volume it's should not be a problem. Im more baffled by the the heat aspect. Cooling is not easy and it's even harder in Arizona. Then again this isn't a server farm so i presume the cooling requirements are lower.
Is it recycled tho, I think someone is stretching the truth. Remember that story about TSMC in Taiwan when they had the drought and they had to get water trucks bring in fresh water from other areas on the island? I didn't even think of the cooling aspect... I will say this, its a great place for solar energy.

Good video...he's wrong when it comes to aquifers though, he said once you use it, its large gone. Surface water seeps through the ground and it replenishes them. Anywho, going back to the video.

www.forbes.com/sites/emanuelabarbiroglio/2021/05/31/no-water-no-microchips-what-is-happening-in-taiwan/
Posted on Reply
#11
Tomorrow
Guwapo77Is it recycled tho, I think someone is stretching the truth. Remember that story about TSMC in Taiwan when they had the drought and they had to get water trucks bring in fresh water from other areas on the island? I didn't even think of the cooling aspect... I will say this, its a great place for solar energy.

www.forbes.com/sites/emanuelabarbiroglio/2021/05/31/no-water-no-microchips-what-is-happening-in-taiwan/
Well as i understand the situation in Taiwan that year was exceptional drought that effected everyone plus there are multiple TSMC fabs there, not just one.
Thus their water needs are naturally higher than a single fab in the US.
Posted on Reply
#12
Guwapo77
TomorrowWell as i understand the situation in Taiwan that year was exceptional drought that effected everyone plus there are multiple TSMC fabs there, not just one.
Thus their water needs are naturally higher than a single fab in the US.
I found that video to be very informative, thank you for sharing it. There seems to be a lot of hopeful optimism in the future of water conservation, I hope it works.
Posted on Reply
#13
Aquinus
Resident Wat-man
WirkoThis makes it easier to create a single point of failure. Shared power lines? Water shortage? Tumbleweeds?
Water is definitely a concern in Arizona, however, power-wise they have quite a diverse portfolio. Between nuclear, hydro, solar, and wind they account for about 46% of Arizona's annual generation. That's a pretty big chunk of renewables. Got to be careful of those tumbleweeds though.
Posted on Reply
#14
Tomorrow
Guwapo77I found that video to be very informative, thank you for sharing it. There seems to be a lot of hopeful optimism in the future of water conservation, I hope it works.
Yep i've been subbed to Asianometry for years. The fun thing i never know what to expect next as he seems to cover wide array of topics from semiconductors to fruits and vegetables. I just happened to remember that he covered the TSMC Arizona water situation lately.
Posted on Reply
#15
londiste
WirkoThis makes it easier to create a single point of failure. Shared power lines? Water shortage? Tumbleweeds?
Probably the opposite - having them together encourages building local supply chain and support services.
Posted on Reply
#16
TheinsanegamerN
Guwapo77Way off topic here... But why in the heck did they both decide to build fabs in the freaking desert? I mean...water is needed and all they have to use is ground water. I would have bult it right off the Mississippi River or around the Great Lakes. That goes for Intel and TSMC...Arizona couldn't give me enough tax deductions to build there.
1) taxes. Arizona is VERY friendly to big business. May of the great lake states, OTOH, are hostile to big business, whether it be due to unionization rules or taxes (Detroit's back tax rule as a prime example).
2) lots of tech workers already present int he area, easier to find people
3) the weather. The areas around the Great Lakes and the Mississippi are very humid, and the lakes have four very strong seasons. Because chip foundries need constant internal conditions to function, building in such an area makes it that much harder to maintain humidity and temperature levels. Arizona, OTOH, is hot and dry year round. Easy to work around. Not impossible, Intel was building that fab in Ohio, but also not ideal. That's a major reason why so many of the early fabs were in SoCal or Texas.
4) Water is 95% recycled, so once things get going the input is relatively low. On the plus side, solar is, well, EVERYWHERE, its arizona, which means these fabs can produce a ton of power with solar to keep the high energy bills in check.
Posted on Reply
#17
Guwapo77
TheinsanegamerN1) taxes. Arizona is VERY friendly to big business. May of the great lake states, OTOH, are hostile to big business, whether it be due to unionization rules or taxes (Detroit's back tax rule as a prime example).
2) lots of tech workers already present int he area, easier to find people
3) the weather. The areas around the Great Lakes and the Mississippi are very humid, and the lakes have four very strong seasons. Because chip foundries need constant internal conditions to function, building in such an area makes it that much harder to maintain humidity and temperature levels. Arizona, OTOH, is hot and dry year round. Easy to work around. Not impossible, Intel was building that fab in Ohio, but also not ideal. That's a major reason why so many of the early fabs were in SoCal or Texas.
4) Water is 95% recycled, so once things get going the input is relatively low. On the plus side, solar is, well, EVERYWHERE, its arizona, which means these fabs can produce a ton of power with solar to keep the high energy bills in check.
Yup, I figured as much about the taxes and solar; however, the rest of the post is well put. I'm going to look into this Detroit back tax business.
Posted on Reply
#18
RogueSix
40K wafers of trash per month. What a literal waste...
Posted on Reply
#19
kondamin
RogueSix40K wafers of trash per month. What a literal waste...
Bit early to call it waste, from what I've been reading A18 will be pretty good at attaining high clocks and there is more software that will benefit from high clock speed than bigger cores with more cache.
Posted on Reply
#20
Baum
Can it produce silicon for ram dies? Would be nice to see intel DRAM branded chips on the market just to make them fully independent, Intel CPU, Intel GPU, Intel Ram, Intel Mobo Chipset :-)
Posted on Reply
Add your own comment
Nov 20th, 2026 16:39 PST change timezone

New Forum Posts

Popular Reviews

TPU on YouTube

Controversial News Posts